Ground work was top priority with hope for concrete this week.
Electrician came through after several days out sick. Plumber devoted almost three whole days. Hot and return for 3 zones of radiant heat. Recirc on the hot water. Four bathrooms on the middle level. Looking at the color coded piping, I think he was kidding when he said rid was hot, blue was cold, white was clear and black was, well, black. My question is what color is for warm water! Whatever, we passed the plumbing inspection.
The engineer (guy in clean shirt) came for second site visit to see for himself if what we are building is what he envisioned. Except for a couple of last minute changes, all was good.
So Wednesday we added 25 yards of mud (that’s was us experts call concrete) to make the beams and the enlarged perimeter.
The slab is the next pour. Not sure when. So many steps before.
Steve
Wednesday, October 10, 2007
Construction Update #28
Subscribe to:
Post Comments (Atom)
No comments: