Construction update #16

Monday gave light to our biggest crew yet. Ed the electrician kept extending conduit, and forgave the concrete process that inadvertently buried the ends of three runs. The surveyors returned to reset  grade lines for the next level up. The excavator guy hob nobbed with the ICF guy and came up with a sorta definite plan on the back fill.

Eric the ICF guy brought in a new guy, Randy. Did great. You could even say he was on fire. Or at least that the sparks from his metal saw went over the bank, and smoldered until actually catching fire! Only about 9 feet square lost.

I looked at and made an offer on a Loader. Renting for so many intermittent uses is cost prohibitive.

The large framed opening is for the Nana wall. Essentially a 14’ wide doorway. The other door on the inside is to the theatre room. Popcorn anyone?

Steve