Construction Update #1


The excavation is finally at its lowest level. The river facing footing is scheduled at 5’ wide. The trench is 7’ wide and then ‘steps up’ to the flat as the footing runs north and will be buried from the outside.

The blue ribbons mark the riparian setback.

The orange ribbons note the grid lines from Hayden’s plans and are outside the building envelope

The rectangular hole is for the elevator shaft.

I will call for the required setbacks inspection.

There is an old travel trailer that I have moved on site. It will serve as a job shack.

Temp power is in place. We have water.

I have two ATV’s to run back and forth between the staging area and the building site. One has a dump bed. The other has a utility trailer attached.

July 9th, here we come.

Steve