Three trucks of CDF on Wednesday. Nine more over the next two days. So now I have walls that truly are 8 feet wide and wider! Wonder what the R value is of that? At least we are done with the CDF for the moment. The flat around the building is now wide enough for equipment to bring in more standard fill.
Laying out the foam floor is essentially done in the area above the bottom level. We can see the bedrooms in outline form. Cool.
On a day when both Eric and I were on the Seattle side doing other things, the Department of Fish & Wildlife show up unannounced and expressed concern about erosion control. Busted. So, the crew tidied up the riparian area and I took time over the weekend to install 34 bales of hay. Hopefully that will alleviate concerns, both real and imagined.
Pipkin returns this week to establish rockeries and carve out the new foundation area. Should be some good visual changes coming up.
Steve
Sunday, September 16, 2007
Construction Update #21